The construction of a roundabout at the intersection of the RM-F43 road and the La Unión crossing "are going at a good pace," said José Antonio Fernández Lladó, Carreteras general director, who said that Phase of replacement of services and construction of sidewalks and has begun to work in the asphalting, paving and construction of islets.
Fernández Lladó announced that "the works will be finished before the end of March".
This roundabout will improve the connection between La Unión and the town of Llano del Beal in Cartagena;
And will facilitate access from the RM-F43 to the Strait of San Ginés and the motorway of La Manga (RM-12).
The roundabout has 34 meters of outside diameter and 22 meters of inner diameter, with a single lane of six meters wide, an interior shoulder of two meters and an outer shoulder of 1.5 meters.
The work involves an investment of 195,802 euros.