Regeneration of Portman will run in two phases, starting in 2013 (13/12/2012)

Barnabas said that "after 23 years of waiting, finally regeneration will be a reality"

The Deputy Secretary General of Communication and regional PP mayor of La Union, Francisco Bernabé, today announced that the Ministry of Environment of Agriculture, Food and Environment "has decided to run the regeneration of Portman Bay in two phases, first bidding place the works for years 2013 to 2015 for 35 million euros and then the remaining work between 2016 and 2017. "

As he explained, "as opposed to four years provided a total investment of 65 million euros, now let's take five, so that in the first three years to run 60 per cent of the works, while in a second phase, which will last around a couple of years, there will be the remaining work "

"This, which is endorsed by the Ministry of Environment and the Department of Sustainability, the Coast and the Sea, which is the body with jurisdiction in the matter, means that regenerates Portman" stressed Barnabas, who has added that the first phase of regeneration is possible by cheap three of the items prescribed.

Thus, "the first is that no dredging will be carried out with a machine-cutter dredger, to understand is that a boat that makes the dredging, but will be done from within the mainland and with machines backhoes, "said.

The second significant reduction in the cost comes to "the decrease in the operating speed of the conveyor belt to take the quarry sterile because they now have a bit longer", while the third is derived from that " of the three large ponds drying sterile had planned only going to do two, being sufficient for deadlines. "

In this sense, the leader is popular has pointed out that "these three cuts in the budget item, they will not affect the quality of the work, is what will allow us to begin the work, predictably, after the summer of 2013, and in 2015 already implemented 60 percent of the work. "

For Barnabas, "the Portman is a very important project that has other related phases, such as the construction of a marina, which will be able to be done simultaneously with the regeneration of the bay, precisely because of these changes that have been mentioned, and all one in urban planning there six DGs involved Autonomous Region ".

"This is a very neat, the town, which is also progressing very well and will result in a reasonable time, perhaps next year, to be able to offer a forecast close to what will be the future management for hotel and tourism developments such high quality that we are advocating for Portman, "he added.

Finally, Francisco Bernabé has valued "very positively" this news, because "after 23 years since the cessation of discharges, nearly a quarter century of delays and broken promises, the work is finally going to start and all that starts, it's over, that's what matters, and along with the marina and the tourist development and sustainable high quality we want for the area, Portman will be the real 'French Riviera' of the Mediterranean Sea. "

Source: PP Región de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información